i. The Civil
Engineering and Development Department HKSAR has appointed MateriaLab Consultants
Limited (MCL) to undertake the Environmental Team services for the Project and
implement the EM&A works.
ii. This is the
eighteenth Quarterly EM&A Report presents the environmental monitoring and
audit works for the period between 1 June 2020 and 31 August 2020. As informed
by the Contractor, major activities in the reporting period included:
June 2020 |
July 2020 |
August 2020 |
· Excavation
and laying of drainage pipe and manhole; · Construction
of SUS structure; · Construction
of District Cooling System; · Utility
laying; · Construction
of road base and road pavement; · Landscape
works – Irrigation system, tree and shrub planting. |
· Excavation
and laying of drainage pipe and manhole; · Construction
of District Cooling System; · Utility
laying; · Construction
of road base and road pavement; ·
Landscape works – Irrigation system, tree
and shrub planting; ·
Laying Cable and Construction for Road Lighting. |
· Utility
laying; · Construction
of road base and road pavement; · Landscape
works – Irrigation system, tree and shrub planting; ·
Laying Cable and Construction for Road Lighting. |
Breaches of the Action and Limit Levels
iii.
No Action and Limit Level exceedance for 24-hr TSP and noise was
recorded in the reporting period at all monitoring stations.
Complaint, Notification of Summons and Successful Prosecution
iv. No environmental complaint and no
notification of summons and successful prosecution were received in the
reporting period.
Reporting Changes
v. The environmental monitoring works of
Contract No. KL/2014/03 will be taken over by Contract No. ED/2018/04 starting
from August 2020. The monitoring results for Contract No. KL/2014/03 will be
directly referred to the results reported in the Monthly EM&A Report for
EP-451/2013 of Contract No. ED/2018/04 subsequently.
vi.
As informed by the ET of Contract No. ED/2018/04, the monitoring
location KTD1a and KER1b have been relocated to KTD1 and KER1 for air and noise
monitoring on 3 August 2020.